Hardware Options Installation
Installing and Removing a Hot-Plug Hard Drive
To install a hot-plug hard drive, first review the installation documentation that came
with the drive.
1. For tower servers, open bezel door.
2. Slide the release latch (1) and remove the hard drive blank (2).
1
2
Figure 3-10: Removing the hard drive blank
HP ProLiant ML350 Generation 3 Server Setup and Installation Guide 3-13
HP CONFIDENTIAL
Writer: Richard O. Heath File Name: d-ch3 Hardware Options Installation.doc
Codename: Steel Venom Part Number: 316354-001 Last Saved On: 12/6/02 3:06 PM