10.
Power up the server (on page 17).
Full-height tape drive
For clarity, the following illustrations include option cabling only.
To install the component:
1. Power down the server (on page 17).
2. Remove the bezel (on page 18).
3. Remove the access panel (on page 19).
4. Remove the applicable media bay blanks ("Remove a media bay blank" on page 20).
5. Disengage the two wire supports inside the half-height drive bays.
6. Install the tape drive:
a. Open the upper and lower wire retainers.
b. Install the full-height tape drive.