HP Performance Optimized Datacenter 40c G2 Site Preparation and Requirements Guide Abstract This document provides site preparation guidance for the
Site requirements 10 Top view clearances shown Side view clearances shown Adequate space around the HP POD 40c G2 is necessary for airflow and co
Site requirements 11 Verify the following clearances prior to delivery: • Working distance clearance—Maintain a safe working clearance according to
Site requirements 12 Grounding feature Specification Grounding electrode conductor pad • The grounding electrode conductor connection bus pad is
Site requirements 13 Requirement Specification Connection 1.9 cm (.75 in) G Adapter to 1.9 cm (.75 in) FPS Hardness No greater than 40°fH (equal t
Site requirements 14 IMPORTANT: The chilled water system piping and heat exchangers must be drained completely, and then purged using compressed a
Site requirements 15 Piping materials Do not use the following interconnecting piping materials in a closed water system: • Oxidizing biocides • A
Site requirements 16 A 1N electrical configuration can be achieved by providing all required electrical feeders from a common power source and from
Supported facility connections 17 Supported facility connections Environmental control system The ECS developed for the HP water-cooled POD is a sta
Supported facility connections 18 Top view shown Connection portal diameter Connection point Quantity 10.16 cm (4 in) portal Main electrical powe
Supported facility connections 19 End view shown You must make the connections between the facility and the HP POD 40c G2. For configuration and in
© Copyright 2012 Hewlett-Packard Development Company, L.P. The information contained herein is subject to change without notice. The only warranties
Supported facility connections 20 Humidifier A dedicated water supply and approved drainage is required for the humidifier. For more information abo
Supported facility connections 21 It is your responsibility to facilitate these connections. HP can make these connections when specifically contrac
Environmental considerations 22 Environmental considerations Environmental risks • Avoid placing the HP POD 40c G2 directly along a drainage path o
Site plan requirements and actions 23 Site plan requirements and actions Completing a site assessment HP requires a detailed site assessment prior t
Site plan requirements and actions 24 • Ensure that the site safety and security programs are properly administered. • Interface directly with the
Site plan requirements and actions 25 • Assembly equipment locations HP POD 40c G2 lifting requirements WARNING: The only approved method for
Site plan requirements and actions 26 • Access landings might be required to maintain the required access to the HP POD 40c G2 electrical panels.
Appendix A: HP site assessment 27 Appendix A: HP site assessment HP POD 40c G2 site assessment checklist During a survey of the readiness of a propo
Appendix A: HP site assessment 28 Item Description Sign-off 8. Clearances Inspect the proposed installation site to confirm clearance requirements
Appendix A: HP site assessment 29 Item Description Sign-off 13. Chilled water infrastructure Determine the overall chilled water capacity, availab
Contents 3 Contents Overview ...
Appendix A: HP site assessment 30 Item Description Sign-off 9. Permission for Photographs Grant HP permission to take photographs for report illus
Appendix B: Preparing for delivery 31 Appendix B: Preparing for delivery Pre-delivery tasks Allow adequate time for planning, scheduling, obtaining
Appendix B: Preparing for delivery 32 Item Description Sign-off 7 When installing on an elevated surface, verify that the maximum height requireme
Appendix B: Preparing for delivery 33 Item Description Sign-off 28 Verify the location of the EPO system external to the powerhouses, if applicabl
Appendix B: Preparing for delivery 34 Item Description Sign-off 3 Verify that the HP Project Team coordinates with other site construction activit
Appendix C: Regulatory compliance notices 35 Appendix C: Regulatory compliance notices HP POD 40c G2 regulatory compliance The HP POD 40c G2 complie
Appendix C: Regulatory compliance notices 36 Cables Connections to this device must be made with shielded cables with metallic RFI/EMI connector hoo
Glossary 37 Glossary AHJ authority having jurisdiction APJ Asia Pacific Japan BMS building management system door A hinged portion of an enclosur
Glossary 38 labeled Equipment or materials to which has been attached a label, symbol, or other identifying mark of an organization that is acceptab
Documentation feedback 39 Documentation feedback HP is committed to providing documentation that meets your needs. To help us improve the documentat
Contents 4 Completing a site assessment ...
Index 40 A about this guide 5 areas prone to lightning or power surges 22 assembly 31 assembly area 24 C cables, FCC compliance 36 Canadia
Index 41 R regulatory compliance identification numbers 35 regulatory compliance, HP POD 40c G2 35 S safety information 6, 10 security 6, 20
Overview 5 Overview About this document This document outlines the site preparation requirements for an HP Performance Optimized Datacenter 40c G2.
Overview 6 Site assessment HP requires a detailed site assessment prior to planning and preparing the customer site location for the HP POD 40c G2.
HP POD 40c G2 capacities 7 HP POD 40c G2 capacities HP POD 40c G2 capacity limitations The capacity limitations for the HP POD 40c G2 are separated
Site requirements 8 Site requirements Site pad The structural design of the HP POD 40c G2 site pad must be based on the specific weight load of the
Site requirements 9 End 1 view clearances shown Top view keep-out clearances shown (shaded areas indicate required clearances)