HP Modular Cooling System Guide de démarrage rapide Page 55

  • Télécharger
  • Ajouter à mon manuel
  • Imprimer
  • Page
    / 93
  • Table des matières
  • MARQUE LIVRES
  • Noté. / 5. Basé sur avis des utilisateurs
Vue de la page 54
Facility planning for implementation 55
Rear view
Raised floor cutouts for the MCS unit
A complete MCS-200/100 installation typically requires the following floor cutouts in a raised-floor facility
(standard rack configuration):
One floor cutout for the chilled water hoses and drain hoses of the cooling unit
One floor cutout for the power cords and data cables of the computer equipment rack, including power
supply to the MCS-200/100. For more information on the top openings, see "Cable openings (on page
26)."
Raised floor panels vary in size globally but create virtual grid lines or seams where panels come together.
These seams are ideal for positioning computer racks on the raised floor. The following figures reference the
locations of rack attributes aligned with raised floor seams to provide critical dimensions for floor cutouts.
MCS-100 floor tile cutouts
Vue de la page 54