Installation
This chapter describes how to install and configure the HP 28684B EtherTwist Hub/12,
HP 28688B Hub Plus, and HP 28699A Hub Plus/48, and verify that they are operating
correctly.
Installation Summary
The steps to install the hubs are:
1. Mount the hub (in a rack, on a wall, or on a table).
2. Plug in the hub and verify its operation.
3. Connect the hub to devices and networks.
4. Customize the hub’s configuration if necessary (for example, because you want to
turn off the unused ports, or, for the HP 28688B and HP 28699A only, because the
hub will be managed remotely from a network management station on an IP
network).
The details for these steps are provided in the rest of this chapter.
Tools and equipment needed for mounting the hub in a rack or on the wall:
Phillips (cross-head) number 1 screwdriver (for rack or wall mounting)
four
5
⁄
8
-inch number 12 wood screws or equivalent (for wall mounting only)
Installation 2-1